Audit of
Procurement activity
Introduction The top management of the engineering company has been extremely happy with the performance of the outsourced internal audit team for the Stores activity (details given in the article in earlier issue of the Journal). The management wants the internal auditors to now assess the procurement activity in terms of process improvements with optimal controls, compliance with laid down systems and procedures and cost rationalisation. The engineering company, whose turnover is 350 crores, is into manufacturing and giving services for cooling appliances like air-conditioners — window, split, cascade etc., refrigerators, water coolers. The auditee has three units, the largest factory located at Thane with other two units at Vapi and Hyderabad. The pro-curement function is centralised at Thane factory with one person each at Vapi and Hyderabad who act as co-ordinators. Total purchases including raw materials, bought-out items, packing materials and consum-ables aggregate to 190 crores. The management feels that there is scope of improving the procurement activity procedures leading to cost rationalisation. The management aim also includes ac-curacy in financial reporting, compliance with applicable laws and regulations. The management objectives are also part of the three pillars of the ‘Integrated Framework — Internal Controls’ by COSO (Committee of Sponsoring Organisations of the Tread-way Commission), USA.
Based on the above background, the partner-in-charge of the internal audit firm had a meeting with his audit manager to chalk out the audit programme. As a first step a flowchart of the ‘procurement activity’ was prepared. Based on the inputs gathered during the flowcharting process and the flowchart, a detailed checklist was prepared for meeting the audit programme objectives. The check-list identified the objectives for this area — Refer Exhibit 1.
Considering that this audit involved large volume of transactions — the software being used in procurement being an ERP, the traditional method of manual vouching would take a lot of time for the audit. It was therefore decided to use a data analysis software — IDEA to carry out a 100% check on all transactions depending on the objectives (using IDEA, the audit for the procurement activity would take only four to five days for the Mumbai — Thane factory). Additionally, back up steps taken in the analysis would also be available in the software. The methodology followed was, to :
Observations arising from the internal audit : Following the checklist and using IDEA, the audit was completed in a two weeks time at the Thane factory. Two more days were spent in collecting external evidence from vendors. Since ‘Procurement’ was a central function, visit to Vapi and Hyderabad was not required and all documentation was available at Thane. Overall, there were number of control weaknesses in procure-ment which were leading to avoidable costs being incurred. A few major observations on systems and procedures are given below :
Materials were purchased from dealers, rather than from manufacturers. This led to an extra cost of Rs.7.8 lacs as worked out from Excise Gate Passes. The study established, in some cases dealer’s margin amounted to 25% to 30%. (Manufacturers give Excise Gate pass which is given to customers based on dealer price and dealers negotiate some more margin to this price based on credit terms, freight and marketing costs. The procurement function should ensure that this margin is not high as the dealer enjoys incentives in the form of turnover discount, various schemes from manufacturer). Recommendation — Prices should be negotiated with the dealers. Possibilities of sourcing materials directly from the manufactueres should be investigated. Cost savings — Based on this input from internal audit, the cost savings were around Rs.5.6 lacs.
o For raw material-formulation and packing material-formulation, quotations are not available from all approved vendors. In turn, no Quotation Comparison Sheets (QCS) have been prepared. Each purchase should have Quotation Comparison Sheet. Recommendation — Quotations should be obtained from more than one supplier, and QCS should be prepared for all orders. Monopoly suppliers should be listed separately, and specific sanction of ‘pro-curement’ committee should be obtained. (Process improvement suggestion).
Benchmark for Purchase Order finalisation by Purchase Committee has been established at Rs.50 lacs and above. Purchase Order analysis shows that only 17 out of 512 Purchase Orders are above Rs.50 lacs during January 2003 to May 2003. Recommendation — There is a need for increasing number of orders being finalised by Purchase Committee. The base may be reduced in the range of Purchase Orders of Rs.10 lacs and above. (Process improvement and cost savings suggestion — Stricter review will lead to better control for major purchases. Action — The base was revised to Rs.10 lacs and above for all Purchase Orders. This revised base was also incorporated in the SOP — Standard Operating Procedure —effective from 1st June 2003).
By-product being sold at Re.1/- per MT, basically to one buyer, while the value of the by-product is much more in the market (The market price was known to the internal auditor as similar by-product was sold by another client). All by-product was sold to one dealer without inviting tenders. Examination of earlier years’ records revealed that by-product had been sold at an average price of Rs.200 per MT, and the same was sold to two or three dealers in a year. This being the case, the internal auditor, with permission from his partner, ap-proached three vendors in the market directly, including two who had supplied earlier, and obtained quotes for the by-product. Sample was drawn from the factory and supplied to these buyers. On receiving the quotes directly from vendors it was observed that the quotes were in the range of Rs.200/- to Rs.220/- per MT. The main reason of this lapse was that by-product sale was not considered to be a purchase activity and was outside the purview of the Purchase Committee. Though transactions were huge, senior officials did not pay attention to the systems and procedures being followed in terms of quotations, vendor analysis, etc. This led to a junior Purchase Official and Stores-in-charge (who certified the disposal) conniving and ensuring that this was handed out at almost no cost to a supplier. The matter was brought to the attention of the Materials Head, Finance Director and CEO. They blacklisted the existing vendor, investigated further and sacked one Purchase Officer and Stores-in-charge and also set up the systems and procedures recommended by the internal auditor. Recommendation — Sale of by-product to be overseen by Procurement Committee and sale to be made on the basis of tender. (Cost-savings and systems streamlining suggestion). Other observations were :
Based on the thorough review and sug-gestions by the internal auditors, the management strengthened the processes leading to a robust procurement process and thus considerable savings to the company. Article by Deepak singhal and manish papalia | |
|
| |
|
| |
|
Rewards waiting for feedback
at | |
|
| |
|
Disclaimer: We believe that the information contained in this e-zine is true. If you do not wish to receive Smart Trainee please click here. | |
|
| |
|
Click here to contact us, if you are unable to view the content properly | |
|
| |
|
| |